Getting electricity connected to your home is a vital step when moving into a new property in Lombok. Whether you’re a local resident, a recent homeowner, or a foreign investor planning your future on this enchanting island, understanding the procedural and legal framework of connecting to the electricity will help you avoid unnecessary setbacks. In this guide, the legal experts at Lombok Lawyers provide a clear and professional overview of what you need to know.

Owner of PT Paja Property Invest
In Indonesia, all aspects of electricity—including generation, distribution, and connection—are exclusively managed by PLN (Perusahaan Listrik Negara), the state-owned power company. As the sole authority in the sector, PLN holds a government-mandated monopoly over the national electricity grid, making it the only legal provider for residential, commercial, and industrial electricity services across the country. Anyone looking to get electricity connected in Lombok must go through either PLN’s official application or office, and follow the installation procedures.
Below are the key procedural steps to follow for obtaining a legal electricity connection in Lombok, through PLN.
Step 1: Conduct a Self-assessment of Your Property
Before applying for an electricity connection in Lombok, it’s important to provide PLN with clear and accurate details about your property. This helps streamline the approval process and avoid delays. Make sure to include the following key information:
1. Exact Location of the Property
Include the full address, land plot number, and nearby landmarks to help PLN locate your site easily.
2. Intended Use of the Building
Clearly state how the building will be used—whether it’s a private residence, rental villa, guesthouse, commercial space, or other purpose. This helps PLN determine the appropriate type of electrical connection.
3. Load Capacity Requirements
Estimate how much power you will need (e.g., 2,200 VA for a small house, 5,500 VA or more for a villa). This allows PLN to determine the appropriate power capacity, estimate the connection costs, and specify the type of meter to be installed. A licensed electrician or PLN representative can help assess your household’s energy requirements, if required.
4. Site Access and Power Infrastructure
Indicate whether your property is accessible by road and whether there are existing power lines in the area. If possible, identify the nearest PLN-connected neighbor and the location of the closest power transformer.
5. Contact Information
Make sure to provide a contact person with an active phone number or email for PLN to reach you for scheduling inspections or follow-up documentation.
Step 2: Prepare the Following Documents
The required document can vary depending on the scale of the property. For a small private house or villa, the required document is generally simple and basic. However, for larger commercial properties—such as hotels, resorts, or industrial buildings—PLN may request additional permits and technical plans. Understanding these distinctions can help you prepare the correct paperwork from the start.
For a small private house or villa:
- Identity card copy (KTP or passport) of the applicant
- Tax Payer’s ID Card
- Electrical Installation Compliance Certificate (SLO)
- Electrical Installation Identification Number (NIDI)
- Site Photos/Videos
- Two Duty Stamps
For Larger Commercial Properties:
- Business Identification Number (NIB)
- Identity card copy (KTP or passport) of the applicant
- Tax Payer’s ID Card
- Electrical Installation Compliance Certificate (SLO)
- Electrical Installation Identification Number (NIDI)
- Site Photos/Videos
- Two Duty Stamps
Please note that both SLO and NIDI are to be issued by the official PLN appointed partners.
Step 3: Submit Your Application
Applications for a new power connection can be submitted via:
- The official website: www.web.pln.co.id
- The PLN Mobile App (available on Android and iOS)
- The nearest PLN branch to your project site.
Step 4: Site Survey
Once your application is accepted, PLN will carry out a site survey to assess the availability of nearby electrical infrastructure—such as transformers and utility poles—for your connection. Based on the results of this survey, the PLN officer will determine whether additional infrastructure is needed. If so, you may be responsible for covering extra costs related to installing a transformer or extending power lines to your property. Ensure that you or your representative is present during the survey.c
Step 5: Connection Day
Once the above steps are completed, the final stage is connection. On the connection day, PLN technicians will visit your property to install the electricity meter and connect your site to the power grid. Make sure the property is accessible and that someone is available to assist or provide access if needed. After the installation is completed and tested, you are required to sign the paper works with the duty stamps you prepared. Now your property is officially energized and ready to use electricity.
Practical Advice
- Anticipate potential delays in remote or underdeveloped areas—communication with PLN official is the key.
- Retain all documents, permits, and payment receipts for future reference.
Key Takeaways
- Provide clear information about your property and the nearest PLN infrastructure.
- Prepare your ID cards, Business ID Card, SLO & NIDI Certificates, Site Phots and duty Stamps.
- Submit your application online or offline, depending on what is applicable.
- Ensure you provide assistance upon site survey and connection.
Follow the guidance above if you need an electricity connection in Lombok. Should you need further assistance, feel free to contact Lombok Lawyers team.